Sedona.biz

Channels
Home
News
Arts & Leisure
Sports
Business
Opinion
Dining
Gardening
Travel
Classifieds
Jobs
Community
Events
Forums
TV Listings

                  Community           

ADOT SR179 construction update for the week of March 24

New Sedona Post Office driveway open March 31

Project 1 (Village of Oak Creek)

Sedona, AZ - Final preparations are wrapping up to switch two-way traffic to the new alignment in the Forest. This week, the new irrigation system will be installed where the salvaged trees have been replanted. Once traffic is switched, the existing alignment will be reconstructed. Upon completion, northbound traffic will be separated from southbound traffic, each traveling on its own alignment.

Paving Operations in the Village of Oak Creek

Paving operations are ongoing in the Village of Oak Creek depending on weather, and the roadway is nearing completion. In the early summer, a layer of rubberized asphalt will be laid on top of the new pavement. This 1/2 inch layer is more temperature sensitive than regular pavement, which accounts for the timing!

High Visibility Crosswalks at Cortez

High visibility crosswalks have been installed at Cortez to encourage pedestrians to use the crosswalks. This was done because many pedestrians were crossing through the middle of the roundabout instead of the designated crosswalks.

Project 2 (Sedona)

New Box Culvert Work Near Morgan Wash

A total of three box culverts and one retaining wall are under construction simultaneously. This week, a new box culvert will be started in the area of Morgan Wash. Progress has been swift on these underground structures, which is good news. The underground works comprises approximately 75% of this improvement project!

New Post Office Driveway

This week, the new Sedona Post Office driveway will be complete. Watch your mailboxes for postcards illustrating the slightly revised post office access.

Sedona Business District Work Starts March 31

ADOT representatives will be visiting with businesses this week to inform them of work beginning between Ranger Road and the Y on March 31. To start, storm drain will be laid from the Y to Ranger on the west side of the road, starting at the Y and working south. The installation of the storm drain from start to finish should take approximately 1 month. After that is done, crews will move on to dirt work, building the grade, and paving, after which they will start work in the roundabout at the Y.



Source:  ADOT

[Home Page] [News Home Page] [Back to Community Page]

   

about us | privacy policy | advertise | bookmark this site

copyright © 2006 Sedona.biz