ADEQ investigating ADOT environmental practices once again on SR179 bridge project
by Ron Vernesoni
SEDONA, AZ (December 24, 2009) - Old bridges like the one at Oak
Creek in Sedona often contain hazardous materials, the worst being
asbestos. Lead was also very prevalent in old bridges. Anytime an
old bridge is demolished in Arizona, the contractor must file
notification with the Environmental Protection Agency (EPA) and/or the Arizona Department of
Environmental Quality (ADEQ) detailing how much asbestos is in the
bridge and how it will be handled. This is required under a federal
law known as the asbestos NESHAPs (National Emission Standards for
Hazardous Air Pollutants).
ADOT started demolition of the
old bridge at least 3 months ago and perhaps earlier, apparently
without filing any notification or work plan.
The photo
taken on September 27, 2009 reveals pieces of the old bridge
deck lying on the creek bed (in the shadows---to the left of
the third new pier, on the left in the forefront). Also
apparent is part of an old pier that has been mechanically
removed (probably saw cut). Also visible are concrete
barriers that were erected as a temporary sidewall on the
old bridge deck.
ADEQ
is currently conducting an investigation to determine if this
notification requirement was met, and whether other applicable
environmental regulations were not properly followed. If the
notification was not met, this is a significant breach of the
federal NESHAP’s environmental law.
The photo above shows that a large section of the old bridge was already previously removed by ADOT, prior to the submission of proper regulatory notification or the submission of a proper work plan. Under the NESHAP regulations, ADOT’s contractor must provide advance notification to the ADEQ for any bridge that is to be demolished, prior to the start of demolition.
Just recently ADOT submitted a
work plan for bridge demolition. The notification is dated
12/2/09. The plan (see
attached) includes the
stripping of lead based paint from bridge railings and girders in
the bridge with a solvent (possibly methylene chloride, which is a
hazardous substance). Bridge demolition always entails the
possibility of encountering asbestos in the bridge structure itself.
Although ADOT did conduct an inspection of the bridge in 2008 for
the presence of asbestos (and found none), no details of this
inspection are provided in the work plan, including where the
samples were taken, how the samples were analyzed, what analytical
techniques were utilized, etc.
The above-referenced work plan
developed by ADOT for the old Tlaquepaque bridge demolition is
wholly inadequate in detail to determine whether or not the public,
the workers, and the environment are being properly protected
throughout the demolition project. The work plan should have been
made available to the public for review and comment many months ago
by ADOT and the City of Sedona in conjunction, given its potential
ramifications.
During my 30 year career as a
professional environmental engineer with a degree in mechanical
engineering from Penn State, I have reviewed many environmental work
plans, including dozens of work plans for the $150 million hazardous
waste cleanup of the Western Processing Superfund site in Seattle,
WA. I served as project manager for the Environmental Protection
Agency for a continuous 3 year period on this site.
In my professional judgment, the
above bridge demolition plan is a very poor quality work plan,
designed to fulfill a bureaucratic requirement, rather than serve as
a working document for demonstration of environmentally safe
demolition of the bridge, and further demonstration of full
protection of the workers and the public.
During the handling of hazardous
wastes involved in the demolition, workers will be required to wear
personnel protective clothing, including half face respirators.
Typically when dealing with hazardous waste on a construction
project, a decontamination reduction zone is set up to prevent
cross-contamination of workers and the surrounding area. No details
are given regarding any decontamination reduction zone, nor are
specific and detailed methods provided for safe handling of
generated hazardous wastes.
The work plan simply states that
“containment pails and visqueen” will be placed below the work
area. What is a containment pail? Are they referring to 5-gallon
buckets? What solvents will be used to strip the paint from the
beams? How will the solvents be stored? No details are given. How
will ADOT determine that all of the lead has been removed from the
beams? What landfill will receive the generated hazardous wastes?
Is it a hazardous waste landfill?
The work plan states that a
catchment mechanism will be placed over Oak Creek (under the
bridge), constructed of steel beams, fence panels, and plastic
sheeting, to catch any material that could inadvertently fall into
the creek. However, the plan does not indicate whether or not the
catchment mechanism will be moved to cover the entire span of the
bridge as the demolition progresses. This is necessary because any
material that falls onto the dry creek bed is subject to washing
downstream during periods of high water flows.
Please note that Oak Creek is an
Outstanding Arizona Water, considered a Tier 3 EPA waterway. Tier 3
waterways are offered extraordinary protection under the Clean Water
Act. No degradation of a Tier 3 water way is allowed to occur.
The work plan states that all work
will be done at night “to ensure the safety of all persons, both
travelers of the roadway and all workers.” If the work is being
conducted in a safe manner, why wouldn’t the work be conducted
during daylight hours when visibility is at a maximum, and emergency
services are most readily available? The work plan is silent on
this subject.
There are many unanswered
questions about this demolition plan. Perhaps the most important
is---what methods and techniques were used to protect the workers,
the public, and the environment during previous demolition
activities for which no work plan was prepared?
Previous ADOT environmental violations at Oak Creek
ADOT
has a history of environmental non-compliance in the state of
Arizona, and therefore their activities must be carefully monitored
by the public until a pattern of consistent compliance is
established.
ADOT
was previously cited by the ADEQ for at least 8 separate regulatory
findings and at least 2 Notices of Violation relative to the bridge
construction work at Oak Creek, in early 2009.
As a result of bridge construction activities, ADOT also exceeded permitted water quality standards in Oak Creek on 12/4/08, 12/11/08, 12/16/08, 12/24/08, 12/31/08, 1/23/09, 1/24/09, 1/25/09, 2/10/09, and 2/19/09.. It is not known what actions, if any, ADEQ took against ADOT for these water quality exceedances.
All
of these violations and exceedances occurred despite the fact that
there is a full-time environmental inspector on site, employed by
ADOT.
ADOT environmental violations at Christopher Creek
In
2002-2003, while involved in construction along Highway 260, ADOT's
contractor built a drainage ditch and bulldozed a total of more than
100,000 gallons of silt-laden stormwater into forest streams in Gila
County. During 2002-2003, the silt drained into several waterways
that flow into Christopher Creek and, later, Roosevelt Lake, with
each discharge lasting from at least one day to two weeks or
longer. Christopher Creek is critical habitat for the spiked dace
and loach minnow, both protected fishes under the federal Endangered
Species Act. The discharged silt changed the color of the surface
water, settled on the creek bottom and formed bottom deposits. The
pollution created risks to aquatic life and recreational uses in the
creek. A civil penalty of $80,000 was issued in 2008 against ADOT’s
contractor.
As a
result of this incident, the ADEQ negotiated a statewide Consent
Order with ADOT that places stringent environmental requirements on
ADOT activities. Obviously the consent decree has been loosely
adhered to, at best.
NEPA implications
Under
the National Environmental Policy Act (NEPA), every major federal
project, such as major highway construction, must undergo either an
Environmental Impact Statement (EIS) or an Environmental Assessment
(EA). An EIS is the most stringent of the assessments; and usually
requires strong environmental mitigation measures to be implemented
during the project.
During project planning, the SR 179 construction project was issued
a Finding of No Significant Impact (FONSI) to the environment by the
EPA, ADOT, and the Federal Highway Administration. In my
professional opinion, this constituted a major error on the part of
the agencies issuing this ruling of insignificance. We are being
asked to believe that a $75 million dollar highway construction
project, which included the above notices of violation, had no
significant impact on the environment, between the Village of Oak
Creek and Sedona. (See item 10 below).
For
your information, “significance” is based on the twin criteria of
context and intensity. Context means the affected environment in
which a proposed action would occur; it can be local, regional,
national, or all three, depending upon the circumstances.
Intensity means the degree to which the proposed action would
involve one or more of the following 10 factors:
1)
Adverse effects associated with “beneficial projects”;
2)
Effects on public health or safety;
3)
Unique characteristics of the geographic area (e.g., historic
resources, park lands, prime farmland, wetlands, wild and scenic
rivers, ecologically critical areas);
4)
Degree of controversy;
5)
Degree of highly uncertain effects or unique or unknown risks;
6)
Precedent-setting effects;
7)
Cumulative effects;
8)
Adverse effects on scientific, cultural, or historical resources;
9)
Adverse effects on endangered or threatened species or designated
critical habitat (pursuant to the Endangered Species Act);
10)
Violations of federal, state, or local environmental law.
The
environmental consulting firm Jones and Stokes, a highly respected
national firm, wrote in a NEPA article that “According to the U.S.
Environmental Protection Agency, federal agencies annually prepare
more than 50,000 EAs leading to FONSIs, contrasted with about 500
EISs. Despite this overwhelming trend, the conclusion of no
significant impact is often not well supported by the accompanying
EA.
ADEQ contact
If
you would like to voice your concerns about the bridge demolition
work, or other environmental aspects of the SR 179 construction
project, you can e-mail the Director of the ADEQ, Benjamin H.
Grumbles, at bhg@azdeq.gov.
Readers' comments
#1Again, nice work by an educated, dedicated volunteer
protecting the public interest. Thank you, Ron Vernesoni!
What has most troubled me about the insensitivity of ADOT in the
SR179 project is the amount of weeds they planted along the
roadside. They sent crews out to dig up tumbleweed, but the
crews failed to remove all of the invasive Russian Thistle.
I contacted the ADOT office and received an email thank you for
my valuable suggestions that all roadside workers be educated to
recognize and remove small plants that spring up, and that the
swath of removal extend as far as tumbleweed can be seen
growing, not just an arbitrary 5 or 8 feet from the curb.
I've not observed evidence either of these suggestions was
implemented.
To tell you how serious this is: The Forest Service has a policy
that construction vehicles driving over Forest Service land must
each and everyone be inspected for weed seeds on their
undercarriage, and if such seeds are found, the vehicle is sent
away to be washed before returning to Forest lands.
The same policies would apply to purity of dirt hauled in and
placed on Forest Service lands.
Tumbleweeds, like Silverleaf Nightshade, are opportunists that
sprout where soil is disturbed. A single tumbleweed may produce
20,000 to 50,000 seeds to be blown further into the forest, or
roll across the highway where it can be hit by a car a scattered
even more directions!
Though it would have been far less-expensive for ADOT to bring
in quality dirt in clean dumptrucks, and carve the road cut with
clean machinery, I don't consider their responsibility to our
environment fulfilled just because they have dug out 70-80% of
this invasive weed.
Area volunteers worked tirelessly prior to this construction to
uproot invasive and noxious weeds all over Forest Service
land--our land. The amount of Russian Thistle that remains along
179 probably exceeds all weeds of all varieties removed by all
volunteers over the past five years.
And even the removal that was done by ADOT was prompted by an
article written by yet another volunteer, Larry Lindahl.
We must all be watchful, and speak out against any polluter,
regardless of the number of their accomplishments or good deeds.
ADOT is acting disrespectfully toward our fragile environment
and the lives of future generations.
Lin Ennis
Readers' Comments - Sedona.biz
SEDONA.BIZ COMMENTS: You can post as a guest (the name you type-in will be displayed but NOT your email), you can login using your Twitter account login info, or you can sign up at Disqus.
To comment as a GUEST, type your comment, name, and
email. (only the name will be displayed not your email).
Click on POST AS GUEST. If you have trouble posting, email editor@sedona.biz, and we'll help.